Midtown Diagnostic Clinic Fit-out
[Deep Review] 6500 SF interior fit-out (MRI, exam rooms, reception). Phased construction in an occupied medical building.
General
- Expected project date commencement and completion not specified in bid document.
- Possible scope gap to allow extras. [1]
- Work restrictions. [2]
- Project manager/site supervisor weekly coordination. [3]
- High-detail schedule to be submitted early. [4]
- Health, Safety and Infection Control [5]
Division 02 Existing Conditions
- Uncertain Conditions of the site. [6]
- Undefined quantity of services [7]
- Review hazardous materials report and include costs. [8]
Division 03 Concrete
- PT scanning and engineering required. [9]
- Approval delay risk to schedule. [10]
- Undefined finish standard. [11]
Division 05 Metals
- Field tolerance and coordination risk transfer to Contractor [12]
- Load verification rests with GC. [13]
- Unbounded fabrication scope. [14]
Division 06 Wood, Plastics & Composites
- Healthcare durability standard casework. [15]
- Potential for unpriced fabrication adjustments. [16]
- Not shown but required expansion clause. [17]
Division 07 Thermal & Moisture protection
- Uncertain quantity and code interpretation risk [18]
- Possible scope expansion. [19]
- Potential for late MEP changes. [20]
Division 08 Openings
- Performance based install expectation. [21]
- Measurement liability. [22]
- Function-driven scope expansion. [23]
- Proprietary system dependency. [24]
- Multi-system testing required. [25]
Division 09 Finishes
- Examination of substrates required. [26]
- Multiple performance obligations. [27]
- Tight flooring requirements. [28]
- Multi-coat painting. [29]
Division 21 Fire Suppression
- Not shown in drawings. [30]
- Local authority inspection/certification. [31]
Division 22 Plumbing
- Unknown site conditions risk. [32]
- Possible underestimation of material and labour for insulation. [33]
- Verfication responsibilty on GC. [34]
Division 23 HVAC
- Unknown base-building capacity and routing constraints. [35]
- Explicit removal of coordination related claims. [36]
- Proprietary system integration needed. [37]
Division 26 Electrical
- Capacity and suitability risk rests with GC. [38]
- Labour variability. [39]
- Less detailed spec. [40]
- Broad obligation for grounding and bonding. [41]